SRINAGAR, JUNE 12: According to the Power Controller, Kashmir Province, in order to carry out 11 kV works at Barsoo Awantipora shut down of 33 kV Awantipora Tap line feeding flour mill shall be observed as per programme below.
During the shutdown, the power supply to the mill fed from the said line shall remain affected on 13 June from 10 am to 5 pm.
Similarly, to carry out the branch cutting of trees and other minor repair works, shut down of 33 kV lines STD-II, Srinagar shall be observed as per programme below.
During the shutdown, the power supply to Receiving Stations K P Bagh, Jawahar Nagar, Rakh Arath, Narakara fed from Bemina-K P Bagh 33 kV line, Danderkhah, Court complex Moominabad Receiving Stations fed from Bemina Exhibition 33 kV line and Batamaloo Exhibition Receiving Station fed from Bemina-Silk Factory 33 kV line shall remain affected on 14 June from 9 am to 5 pm.